Google
×
Wyświetlam wyniki dla crash time ii
Zamiast tego wyszukaj crash_time_iii
crash time ii z books.google.com
A. M. Natarajan. 76. The following Table gives data on normal and crashed time and cost for a project. Activity Time (in weeks) Cost (`) Normal Crash Normal Crash 1-2 9 4 1,300 2,400 1-3 15 13 1,000 1,380 2-3 7 4 7,000 1,540 2-4 7 3 1,200 ...
crash time ii z books.google.com
... time from normal to crash completion. The steeper the slope of the line, the more expensive it is to reduce the ... (ii) Crash cost and time: Crash cost is the minimum cost of carrying on any activity using additional resources, and the ...
crash time ii z books.google.com
... II (type of works where they can be used) is Column I P. Unit price contract Q. Lump-sum contract R. Percentage ... time curve. 1. It is given by difference between normal cost and crash cost divided by crash time. 2. it is given by ...
crash time ii z books.google.com
... time ii) Pessimistic time iv) Most likely time. 11. Differentiate between CPM and PERT. 12. Explain cost analysis in the network. 13. Explain (i) Direct cost ii) Indirect cost 14. Define (i) Normal time (ii) Crash time iii) Normal cost iv) ...
crash time ii z books.google.com
Godfred Kwame Abledu. ii. Find the cost associated with the normal duration time. iii. Find the shortest possible ... Crash duration Crash cost A - 4 25 3 37 B A 4 16 4 16 C - 5 35 2 75 D A , C 8 49 7 95 E B , C 8 60 4 130 F D ,E 6 41 3 ...
crash time ii z books.google.com
... ( ii ) Find the critical path and the project duration for the Case ( i ) . ( iii ) Find the optional schedule and optional project duration . 97. The activities of a project and their normal and crash time ... Crash Time Cost Time Cost 1-2 6 ...
crash time ii z books.google.com
... 2–4 50 E 3–4 - F 2–5 30 G 4–5 70 (d) Crashing the project. Crashing Options Cost (Rs) Decision Project Duration Critical Path First (i) 1–2 30 Crash 1–2 12 1–2–4–5 (ii) 2–4 50 (iii) 4–5 70 Second (i) 2–4 50 Crash 2–4 11 1–2–4–5 (ii) 4–5 70 ...
crash time ii z books.google.com
... 2 - 4 - 7-9 ( B ) 1-3-6-8-9 ( C ) 1-3-5-7-9 ( D ) Both A & B 98. Formula for cost slope is ( A ) Cost slope = Normal time - Crash time Crash Cost - Normal cost ( B ) Cost slope = ( C ) Cost slope = ( D ) Cost slope = Crash time - Normal ...
crash time ii z books.google.com
... 2 - 4 - 7-9 ( C ) 1-3-5-7-9 ( D ) Both A & B 98. Formula for cost slope is ( A ) Cost slope ( B ) Cost slope ( C ) Cost slope = ( D ) Cost slope = ( 8 ) 15 Normal time - Crash time Crash Cost - Normal cost Crash time - Normal time Crash ...
crash time ii z books.google.com
... 2 - 4 - 7-9 ( C ) 1-3-5-7-9 ( D ) Both A & B 98. Formula for cost slope is ( A ) Cost slope ( B ) Cost slope ( C ) Cost slope = ( D ) Cost slope = ( 8 ) 15 Normal time - Crash time Crash Cost - Normal cost Crash time - Normal time Crash ...